< Return to Samples

viper

Viper Plagiarism Scan

Plagiarism Report For '482950-507021.docx'

Viper scans your work against over 10 billion web pages as well as any work previously submitted to our firm. Once the scan is completed, the report highlights content that may match these other sources, including links to the relevant sites.

However, not all matching content is a negative thing. Examples of acceptable matching content include: quotations, reference lists/bibliographies, the essay title or question, tables and charts, appendices, and common terminology and phrasing.

Overall plagiarism rating 10% or less : The results show that it is highly unlikely that this document contains plagiarised material. A careful check will only be necessary if this is a lengthy document.

Overall plagiarism rating 11% - 20% : The results show that there is a low risk that the document contains any plagiarised material. Most of the matching content will probably be fragments. Review your report for any sections that may not have been referenced properly.

Overall plagiarism rating 21% + : The results show that there is a moderate risk that the document contains plagiarised material. If the overall rating is this high, you need to check your report very carefully. It may be that the bibliography or quotations have caused this, but it is critical that you go through the document and review the areas that the scan has flagged to try to reduce this percentage.

Document Text


482950 word
Literature Review
Introduction
The purpose of this chapter is to ascertain the bank of research carried out to date on the topic of causes and effects of delays in construction projects in the UK.
Terminology
This research focuses on delays in the construction industry and the impact of such delays on project success, as such it is prudent to understand terminology such as delay and success in the context of this study.
Success Criteria in Construction Projects
Mir and Pinnington (2014) point out that within the construction industry there is a myriad of project types and sizes, with different levels of uniqueness and complexity, which suggests that the criteria for success varies, as such there is no universal set of success criteria. Muller and Jugdev (2012) make a similar claim, maintaining that process success is multi-dimensional influenced by the perspectives of the stakeholders and factor such as the type of contract. Mir and Pinnington (2014) add that success can be measured in terms of value to the client, a point that is reinforced by the Office of Government Commerce (OGC, 2007), which argues that success should be measured in terms of the value offered to the client. Walker (2015) maintains that success in the construction industry is defined in terms of a project delivered on-time, within budget and to the quality and functionality anticipated by the client/ employer. Fewings (2013) agrees, adding that the concept of success should be viewed from the perspective of the construction team and the end-user, where the former is likely to also consider success in terms of the end-users satisfaction and commercial success in terms of profitability, whilst the end-user is likely to measure success in terms of functionality, comfort and operational costs over the life of the asset. Given this discourse, it is submitted that success equates to a project which adds value to the project stakeholders, measured in terms of time, costs, quality and profitability.
Delay
Construction delay occurs when a project is executed later than planned, or delivered outside of the time specified in the contract (Haseeb et al.,2011). Fugar and Agyakwah-Baah (2010) make the point out that the causal factors in delays can be divided into two categories, namely internal causes and external causes. Gardezi et al.,(2014) take the view that delays can be defined in terms of inexcusable delays and excusable delays, where the former are caused solely by the contractor and as such the contractor is not entitled to compensation for such an event and is also required to expedite the works and/or compensation the client for losses incurred due to the delay. Kikwasi (2013) maintains that excusable delays can be further categorised as non-compensable delays and compensable delays. Non-compensable delays are generally caused by parties outside the project, or by events that are beyond the control of the project team, such as acts of God, unusual weather, fires or acts of government. In these instances, a contractor is entitled to a time extensions but is not entitled to financial compensation for delay damages. In contrast, compensable delays are caused by the client or the client’s agent and include actions such as the late release of drawings. In short, an excusable, compensable delay typically results in an extension to the project schedule which in turn permits the contractor to claim additional costs from the client. Such a claim will include the additional indirect costs incurred by the contractor such as office overheads (Gardezi et al.,2014).
Fugar and Agyakwah-Baah (2010) argue that internal causes of delay are due to the primary stakeholders, including the client, the contractor and the designer. These delays can be controlled through effective management of the contract and the construction process. In contrast external causal factors such as weather cannot be controlled by the project team. The point being that delay is caused by a combination of factors, as such it is important to understand the underlying causes of delay from the internal and external perspective.
Underlying factors for delays in construction
There are several factors that contribute to the risk of delay in construction projects, including contractual relations, site conditions, the availability of resources (Haseeb et al.,2011). According to Doloi et al., (2012) the problem of delay is endemic in the global construction industry, with a range of studies highlighting commonalities in the causes of delay. Delays due to internal factors can be categorised as client-led, designer-led or contractor -led. Muhwezi et al., (2014) make a similar differentiation, inferring that delay is typically a combination of these factors, given that for example design changes may lead to rework on site, creating a cumulative effect in extending the time taken to complete a project.
Client-led delays include practices such as late approval of drawings and method statement, slow payment of invoices, lack of agreement about key responsibilities in the contract and changes to the design data during the construction period (Doloi et al.,2012). Rosenfield (2013) adds that the client can also create problems which affect delays during construction by choosing unrealistic tender-prices and selecting the lowest price tender over value.
Contractor-led delays include poor financial management by the contractor, inadequate contractor’s experience. Other factors include poor site management and delay in site mobilisation, which can be related to frequent changes during the construction process (Shehu et al.,2014). Khoshgoftar et al.,(2010) agree that the contractor can be responsible for significant delays in a project if there is failure to control time and cost, a lack of quality control of workmanship leading to mistakes and rework and failure to resource a project with sufficient materials and experienced labour.
The designer is also responsible for delays during the construction stage of a project’s lifecycle, due to design errors, poor quality management during the design process and inadequate site investigation (Muhwezi et al.,2014). It is argued that in some instances, the client is in part responsible for these design problems, due to insistence on going to tender before the tender package has been completed in sufficient detail (Rosenfield 2013).
Khoshgoftar et al.,(2010) conducted a detailed review of research on delays in construction and concluded that this problem is due to a combination of inter-related factors, such as ineffective planning and scheduling during the design and the construction stage, as well as poor resource management in the construction stage. Inadequate client finance can lead to delays in construction, particularly if this problem affects the client’s ability to make payments on-time. A key underlying issue in delay causation is a lack of communication between the project parties.
Impact of these delays in terms of time, cost and quality
According to Abdul-Rahman et al.,(2011), the impacts of delays in construction can be assessed in terms of the national impacts which adversely affect the industry’s contribution to the economy and employment; at an industry scale, where delays affect productivity and profitability and at a project scale where delays result in dissatisfied clients, low levels of profit and financial hardship for the contractor. Haseeb et al.,(2011) take a similar view, insisting that at a project-scale, delay results in a loss of income for the contractor and potentially for the client, as the former experiences higher costs due to longer work time, along with increased labour costs. Fugar and Agyakwah-Baah (2010) take a similar stance, arguing that delays often lead to cost overrun, disputes and litigation. These factors result in lose and hardship for the client, with additional expense for the contractor in terms of the standby costs of workers and equipment.
Meng (2012) makes an important point, arguing that delay can affect the willingness to communicate, which in turn affects the outcomes of the project and can lead to conflict and disputes. It is suggested that this is particularly important in an industry that is already fragmented through competitive tendering and the contractual nature of the project environment.
Mitigation measures used to reduce delays
Olawale and Sun (2010) take the view that delays and cost overruns are due to ineffective project control. There are several methods that can be used to control time, reducing the risk of delays including the use of relatively basic techniques such as Gantt Charts, which offer a time related bar chart for project stakeholders. The construction industry also used a process referred to as the critical path method (CPM), which unlike the Gantt chart takes account of the different elements of the work that are critical to completing the project on-time. There are also more sophisticated methods of time-control and management such as Technique, Performance Evaluation Review Technique (PERT) and Precedence Network Diagram (PND), as well as Elemental Trend Analysis/Line of Balance (LOB), and software packages such as Microsoft Project and Primavera. In short there is a host of processes available to the contractor to control time and optimise success. However there are multiple and overlapping causal factors driving delays in construction, as such in addition to time control processes, a contractor needs to implement risk management to predict factors which could affect the time taken to complete the project and to have measures in place to combat such risks (Iqbal et al.,2015; Zavadskas et al.,2011). In addition, the preceding section highlighted the impact of change during construction on delays, as such it is argued that a contractor should have a change management process in place to quantify the impacts of change prior to implementing such change (Bröchner and Badenfelt 2011; Shen et al.,2010).
Summary
In summary it is suggested that delays in construction are driven by a range of factors including client, designer and contractor-led issues. The impacts of these delays include loss of profit, productivity and reputation, as such this problem requires attention. It is submitted that there are processes available to a contractor to mitigate such problems including risk, value and change management, which offer the potential to control the internal and external factors driving delays.
References
Abdul-Rahman, H., Wang, C., Takim, R. and Wong, S., 2011. Project schedule influenced by financial issues: Evidence in construction industry. Scientific Research and Essays, 6(1), pp.205-212.
Bröchner, J. and Badenfelt, U., 2011. Changes and change management in construction and IT projects. Automation in Construction, 20(7), pp.767-775.
Doloi, H., Sawhney, A., Iyer, K.C. and Rentala, S., 2012. Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), pp.479-489.
Fewings, P., 2013. Construction Project Management: An Integrated Approach. Abingdon: Routledge.
Fugar, F.D. and Agyakwah-Baah, A.B., 2010. Delays in building construction projects in Ghana. Construction Economics and Building, 10(1-2), pp.103-116.
Gardezi, S.S.S., Manarvi, I.A. and Gardezi, S.J.S., 2014. Time extension factors in construction industry of Pakistan. Procedia Engineering, 77, pp.196-204.
Haseeb, M., Bibi, A. and Rabbani, W., 2011. Problems of projects and effects of delays in the construction industry of Pakistan. Australian journal of business and management research, 1(5), pp.41-50.
Iqbal, S., Choudhry, R.M., Holschemacher, K., Ali, A. and Tamošaitienė, J., 2015. Risk management in construction projects. Technological and Economic Development of Economy, 21(1), pp.65-78.
Khoshgoftar, M., Bakar, A.H.A. and Osman, O., 2010. Causes of delays in Iranian construction projects. International Journal of Construction Management, 10(2), pp.53-69.
Kikwasi, G., 2013. Causes and effects of delays and disruptions in construction projects in Tanzania. In Australasian Journal of Construction Economics and Building-Conference Series (Vol. 1, No. 2, pp. 52-59).
Meng, X., 2012. The effect of relationship management on project performance in construction. International journal of project management, 30(2), pp.188-198.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.
Muhwezi, L., Acai, J. and Otim, G., 2014. An assessment of the factors causing delays on building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), pp.13-23.
Muller, R. and
Jugdev, K., 2012. Critical success factors in projects, Pinto, Slevin, and Prescott—the elucidation of project success. International Journal of Project Management, 5 (4), pp.757–775.
Office of Government Commerce, 2007. Achieving Excellence Guide 3. Project procurement lifecycle the integrated process. London: OGC.
Olawale, Y.A. and Sun, M., 2010. Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construction management and economics, 28(5), pp.509-526.
Rosenfeld, Y., 2013. Root-cause analysis of construction-cost overruns. Journal of Construction Engineering and Management, 140(1), p.04013039.
Shehu, Z., Endut, I.R., Akintoye, A. and Holt, G.D., 2014. Cost overrun in the Malaysian construction industry projects: A deeper insight. International Journal of Project Management, 32(8), pp.1471-1480.
Shen, W., Hao, Q., Mak, H., Neelamkavil, J., Xie, H., Dickinson, J., Thomas, R., Pardasani, A. and Xue, H., 2010. Systems integration and collaboration in architecture, engineering, construction, and facilities management: A review. Advanced engineering informatics, 24(2), pp.196-207.
Walker, A., 2015. Project management in construction. Chichester: John Wiley & Sons.
Zavadskas, E.K., Turskis, Z. and Tamošaitiene, J., 2010. Risk assessment of construction projects. Journal of civil engineering and management, 16(1), pp.33-46

< Return to Samples